IKN legislative complex 25.4%, judicial area 32.83% complete

Also under review: the 243,000-cubic-meter SM-02 retention pond is 70% complete, and PT Star Bright's investment totals Rp1.25 trillion.

Construction of the legislative complex in Ibu Kota Nusantara has reached an average physical progress of 25.40 percent, while the judicial complex is 32.83 percent complete. Basuki Hadimuljono, head of Otorita IKN, inspected the work at Kawasan Inti Pusat Pemerintahan Nusantara on Thursday, 12 November 2026. In the legislative area, progress was recorded at 22.75 percent for the DPD RI building, 24.33 percent for MPR RI, 21.91 percent for DPR I, 21.66 percent for DPR II, and 20.25 percent for the plenary hall; the legislative area road reached 41.49 percent. In the judicial area, the Mahkamah Agung building and Plaza Keadilan were 26.52 percent complete, while the Mahkamah Konstitusi building and Komisi Yudisial stood at 25.27 percent; the judicial area road reached 46.69 percent. Otorita IKN also reviewed PT Star Bright International Investment's Rp1.25 trillion project and the SM-02 retention pond, which has a capacity of 243,000 cubic meters and is already 70 percent complete.

Sources

  • RepublikaTier 175% reliableRead →28 hours ago
  • CNN IndonesiaTier 180% reliableRead →4 hours ago

Series

Ibu Kota Nusantara · Government Core DevelopmentSee every chapter in this series →

Subjects

IKN legislative complex 25.4%, judicial area 32.83% complete — Veloxia Global News